Construction at Malvern Hill is progressing very well, and residents can expect to move into their new home this year in Nov / Dec.


- Top floor steel structure is nearly complete.

- Construction of utility rooms in basement is nearly complete.

- Levels 3 and 4 concrete structures have been stripped and cleaned, preliminary services rough in has commenced.

- Internal plasterboard sheeting to walls and ceilings and sliding door frames to apartments on levels 1 and 2 is progressing well.

- Windows and external door installation to apartments on levels 1 and 2 is well advanced.

- Application of external finishes to the building has commenced.

 