We are pleased to advise that Fifty Albert is moving along well and is on schedule for completion mid 2013.
- Lower ground concrete slab – 100% complete
- Ground slab formwork and reinforcement – 100% complete
- Paving slab around heritage house – 100% complete
- Lift core and stairwell – Complete to level 2
- Lower ground to ground Pre cast and in-situ columns – 100% complete
- Ground to level 1 columns – 20% complete
- Lower ground to ground Pre cast panels to southern boundary – 100% complete
- Ground to Level 1 pre-cast panels to Southern Boundary – 10% complete